HOW IS THE PROJECT OF 鈥淰N DANANG - RENTAL BUILDING HALL 3 ELECTRIC - DRAEXLMAIER AUTOMOTIVE 鈥 PHASE 2鈥 CURRENTLY?
By the end of July 2022, the project has completed 53% of the work volume (while only 45% of the time has passed). The team has completed the renovation of the roof ventilator of the Hall 3 Factory, and the reinforcement of the existing roof of Hall 3.
Updated August 2, 2022
HAPPY DUNG QUAT PROJECT - PHASE 4 AHEAD THE CONSTRUCTION PROGRESS
Up to now, the project has been implemented for 4 months, the Site Management Board of Happy Dung Quat - Phase 4 project has completed 80% of the work. 海角社区 is rushing to implement the final works such as concrete pouring, workshop foundation, and steel work. With the current progress, 海角社区 is confident to finish the project 1 month earlier than contracted but still ensure the highest quality.
Updated July 23, 2022
SANGSHIN CENTRAL VIETNAM PROJECT FOR ACHIEVING THE SAFETY CERTIFICATE
Congratulations on SangShin Central VietNam project for achieving the safety cerificate of June 2022.
Updated July 7, 2022
VIDEO OF CONSTRUCTION PROGRESS OF CHAN MAY QUARTZ MACHINING FACTORY IN HUE AFTER 1 MONTH OF COMMENCEMENT
Video of Construction progress of Chan May Quartz Machining Factory in Hue after 1 month of commencement. Update on 01.06.2022.
Updated June 15, 2022
GROUND-BREAKING CEREMONY OF SANGSHIN CENTRAL VIETNAM PROJECT
In the morning of June 1, 2022, at Ai Tu commune, Trieu Phong district, Quang Tri province, 海角社区 Engineering and Construction Corporation solemnly held the Groundbreaking Ceremony of Sangshin Central Vietnam project.
Updated June 2, 2022
HOW IS THE PROGRESS OF HAPPY FURNITURE PHASE 4 PROJECT?
Happy Furniture Phase 4 project was started by 海角社区 General Contractor on February 11, 2022 and expected to be completed on August 31, 2022.
Updated May 26, 2022
Copyright 海角社区2025. All rights Reserved.
Powered by