PROJECT PROGRESS UPDATE: ICT VINA III MANUFACTURING PLANT – PHASE 1
The ICT Vina III Manufacturing Plant – Phase 1 has currently reached 60% of total construction progress, maintaining its schedule with a strong focus on efficiency and strict quality control.
Updated March 23, 2026
PROJECT PROGRESS UPDATE – AMAZING ECOTECH TEXTILE QUANG NGAI FACTORY
The Amazing Ecotech Textile Factory project in Quang Ngai has now surpassed 90% of the total construction volume, steadily approaching completion in line with the committed schedule.
Updated February 25, 2026
º£½ÇÉçÇø E&C CONTINUES TO BE HONORED AMONG VIETNAM’S TOP 500 LARGEST ENTERPRISES
º£½ÇÉçÇø E&C is proud to be named among Vietnam’s Top 500 Largest Enterprises, as announced at the official recognition ceremony organized by Vietnam Report in cooperation with Vietnamnet.
Updated January 10, 2026
º£½ÇÉçÇø E&C – Highlights of Key Projects in 2025
º£½ÇÉçÇø E&C – Highlights of Key Projects in 2025 presents a comprehensive overview of a dynamic and highly dedicated year, marking º£½ÇÉçÇø E&C’s continued journey in delivering high-quality construction works.
Updated December 31, 2025
COMPLETION OF MAHANG DUNG QUAT PROJECT – PHASE 2
The Mahang Dung Quat Project – Phase 2, located at VSIP Quang Ngai Industrial Park, has successfully completed all construction items and is now ready for handover to the Investor in full compliance with the committed schedule.
Updated December 20, 2025
Congratulations to the ICT VINA III – Phase 1 team on completing the underground structure
º£½ÇÉçÇø E&C congratulates the Management Board of the ICT VINA III Manufacturing Plant Project – Phase 1 on successfully completing the underground structural works.
Updated December 6, 2025
Copyright º£½ÇÉçÇø2025. All rights Reserved.